|
|||
|
Goal 7.0 SUSTAIN EXCELLENCE IN OPERATING,
MAINTAINING, AND RENEWING THE Facility AND
INFRASTRUCTURE PORTFOLIO TO MEET LABORATORY NEEDS
|
ELEMENT | Letter Grade | Numerical Score | Objective Weight | Total Points | Total Points |
---|---|---|---|---|---|
7.0 SUSTAIN EXCELLENCE IN OPERATING, MAINTAINING, AND RENEWING THE FACILITY AND INFRASTRUCTURE PORTFOLIO TO MEET LABORATORY NEEDS | |||||
7.1 Manage Facilities and Infrastructure in an Efficient and Effective Manner That Optimizes usage and Minimizes Life Cycle Costs | B- | 2.6 | 50% | 1.30 | |
7.2 Provide Planning for and Acquire the Facilities and Infrastructure Required to Support Future Laboratory programs | B+ | 3.4 | 50% | 1.70 | |
Performance Goal 7.0 Total | 3.00 |
7.1a - SLAC identified a goal of 1.0% for MII in FY06 in the Ten Year Site Plan. The total planned maintenance expenditure stated in the Ten Year Site Plan for FY06 was $8.5m with an RPV of $850m, yielding the 1% goal. The actual expenditure was $9.3m resulting in a improved MII of 1.1% though this is under the SC MII goals of 2.0%.
In the FY2007 – FY2016 TYSP (submitted in June 2005) SLAC set $8.323 million as the target for the FY2006 maintenance budget. In the FY2008 – FY2017 TYSP (submitted in June 2006) the $8.3 million figure was confirmed, with carryover funding included, as the targeted actual spend. The actual maintenance cost for FY2006 was $9.3 million. Using the RPV of $904,804,001 that was current until August, 2006, SLAC’s MII was 1.03%.
SLAC believes that a maintenance expenditure of 2% of RPV, or about $18 million, would have had a significant negative impact on its research program and is not warranted because the Laboratory’s deferred maintenance is only $31 million. A contractor has recently recalculated the RPVs for the nineteen unique site buildings and underground structures (which comprise nearly one-half of the site square footage) and a proposal will be submitted to DOE by end of October 2006 to adjust the RPVs for these high value, low maintenance facilities, for the MII determination, to a value commensurate with the systems and components that require maintenance.
7.1.b DM reduction goal for FY06 is $125k as stated in the Ten Year Site Plan. Our actual DM reduction exceeded this amount as all facilities shops spend two days a month of effort dedicated to DM reduction and credit has been taken for projects that result in DM reduction. We are also doing a better job of tracking DM reduction work.
7.1.c(1) SLAC is achieving an 85% completion rate for scheduled fleet services maintenance and 80% for scheduled HVAC preventative maintenance. Staffing limitations and access restrictions are controlling the performance in this area. We are not currently prioritizing preventive maintenance items in a consistent way. This will be improved next year as part of the CMMS implementation and in FY07 we expect to finish all the highest priority PMs on schedule.
7.1.d SLAC completed all of the energy goals for FY06 that were not contingent on the availability of funding. The complete FY06 Energy Management Report will be submitted by the end of November to the Energy Manger of Office of Science instead of being attached to the Performance Measures as directed by the Energy Manger in September.
7.2.a Effective integrated planning for the acquisition, utilization, maintenance, recapitalization and disposition of real property. The target was 100% of integrated planning milestones identified and agreed to by DOE-SC and SLAC in the areas of deferred maintenance, maintenance plan, FIMS and Rehab and Improvement Cost
SC DMR Funding Goal (000) | Site DMR Funding Plan (000) | Estimate of DM at the end of the Fiscal Year (000) | Estimated ACI (estimated DM/ estimated RPV) | |
---|---|---|---|---|
FY 05 | NA | NA | $ 21,290 | 0.98 |
FY 06 | NA | Additions: $8,246, Inflation: $679, Reductions: GPP $445, Operating Funded $260 | $ 29,510 | 0.97 |
FY 07 | 792 | Additions: $1,200, Inflation: $706, Reductions: SLI SORI $2,682, GPP $1,176, Operating Funded $1,087 | $ 26,472 | 0.97 |
FY 08 | 1440 | Additions: $1,250, Inflation: $638, Reductions: SLI SORI $6,484, GPP $225, Operating Funded $2,173 | $ 19,477 | 0.98 |
FY 09 | 2100 | Additions: $1,300, Inflation: $478, Reductions: Operating Funded $2,810 | $ 18,445 | 0.98 |
FY 10 | 2760 | Additions: $1,350, Inflation: $455, Reductions: Operating Funded $2,760 | $ 17,490 | 0.98 |
FY 11 | 2760 | Additions: $1,200, Inflation: $430, Reductions: Operating Funded $2,760 | $ 16,360 | 0.98 |
FY 12 | Additions: $1,250, Inflation: $405, Reductions: Operating Funded $1,693 | $ 16,322 | 0.99 | |
FY 13 | Additions: $1,300, Inflation: $405, Reductions: Operating Funded $1,800 | $ 16,228 | 0.99 | |
FY 14 | Additions: $1,350, Inflation: $404, Reductions: Operating Funded $1854 | $ 16,128 | 0.99 | |
FY 15 | Additions: $1,400, Inflation: $403, Reductions: Operating Funded $1,910 | $ 16,021 | 0.99 | |
FY 16 | Additions: $1,450, Inflation: $402, Reductions: Operating Funded $1,967 | $ 15,906 | 0.99 | |
FY 17 | Additions: $1,500, Inflation: $400, Reductions: Operating Funded $2,144 | $ 15,662 | 0.99 |
7.2 b The SORI project is within 5% of target for cost and schedule. Cumulative costs to date are $5,130K in accrued and committed funds. The cost (cost and committed funds) target is $5,334K for a percentage of 96% which is within the -5% target for cost. The lower tier milestone targets are expected to be one month late. CD3 was achieved as scheduled. Letter grade is B+.
7.3 c Effective execution of facility and infrastructure projects greater than $250K for FY06. Letter grade is B+.
Project | Budget ($K) | Cost ($K) | Cost to Budget | Cost Variance | Weighting Factor | Weighted Variance | Schedule Status |
---|---|---|---|---|---|---|---|
51-75 A&E restroom ADA retrofit | $270 | $256 | 94.8% | 5.2% | 0.026 | 0.14% | Complete |
52-36 Research Yard Cooling Tower | $1,882 | $1,887 | 100.3% | -0.3% | 0.184 | -0.05% | Complete |
52-49 Klystron Gallery Equip grounding | $397 | $397 | 100.0% | 0.0% | 0.039 | 0.00% | Complete |
52-50 Upgrade Sub 7 | $1,220 | $1,226 | 100.5% | -0.5% | 0.119 | -0.06% | On schedule |
52-51 Upgrade SCS 1st and 2nd floor | $450 | $444 | 98.7% | 1.3% | 0.044 | 0.06% | On schedule |
52-57 ESB/Test Accelerator Seismic | $237 | $200 | 84.4% | 15.6% | 0.023 | 0.36% | On schedule |
53-24 Secondary Containment upgrade | $332 | $308 | 92.8% | 7.2% | 0.032 | 0.23% | On schedule |
54-40 Light Assembly Building Sub | $1,589 | $1,589 | 100.0% | 0.0% | 0.155 | 0.00% | Complete |
55-35 SLAC 10gb Network upgrade | $823 | $823 | 100.0% | 0.0% | 0.080 | 0.00% | Complete |
55-40 Bldg 081 Elect upgrade | $333 | $306 | 91.9% | 8.1% | 0.033 | 0.26% | Complete |
55-55 Cooling Tower Chem. Hut | $285 | $75 | 26.3% | 73.7% | 0.028 | 2.05% | On schedule |
55-60 GLAST Operations Facility | $572 | $463 | 80.9% | 19.1% | 0.056 | 1.06% | On schedule |
55-65 Directors Office remodel | $500 | $483 | 96.6% | 3.4% | 0.049 | 0.17% | On schedule |
56-50 Bldg 050 1st floor Water Cooled Racks | $298 | $219 | 73.5% | 26.5% | 0.029 | 0.77% | On schedule |
56-75 RA2 and RA4 Switchgear replacement | $462 | $439 | 95.0% | 5.0% | 0.045 | 0.22% | On schedule |
14-0016 FFTB Waste Disposal | $337 | $300 | 89.0% | 11.0% | 0.033 | 0.36% | On schedule |
14-0170 Bldg 040 and 084 lighting | $252 | $252 | 99.9% | 0.1% | 0.025 | 0.00% | Complete |
Totals | $10,239 | 1.000 | 5.59% |