Skip to main content.
banner SLAC

 

 

 

 

 

16. FY 06 FOURTH GENERATION SOURCE DEVELOPMENT – THE LINAC COHERENT LIGHT SOURCE PROJECT
by Mark Reichanadter 
Appendix B Self-Evaluation FY2006

Return to Table of Contents

Project Authorization Milestones – The Project received approval of Critical Decision 3-B (Approve Start of Full Construction), in February 2006.

Environment, Safety and Health – A general safety coordinator and an expert construction safety coordinator provide safety expertise and support the LCLS organization throughout 2006. LCLS has in place a functioning Integrated Safety Management System (ISMS) through 2006. The LCLS project recordable incident rate is currently 0.63 (The number of injuries sustained by an average crew of 100 individuals over one year.). This compares favorably to general industry rates of 6.8 and that of the Department of Energy with is 2.1 for similar work. LCLS released the final draft of the Fire Hazards Analysis (FHA) for internal and DOE review and comments in June 2006. The FHA was approved and issued on schedule, in mid-July 2006.

Management – The LCLS management team was strengthened by adding two Associate Project Directors (Civil Construction and Engineering). Also, the LCLS procurement organization, 100% dedicated to LCLS but reporting to the SLAC Business Services Division Director, has been augmented by securing two procurement consultants with significant experience in DOE procurements and civil construction. The LCLS also hired a full-time Controls Manager who is responsible for integrating the existing SLAC controls infrastructure with the LCLS controls systems.

2006 marked the start of the delivery of the LCLS Long-Lead Procurements (LLP). In particular, LLP for the LCLS undulator titanium strongbacks, magnet poles and magnet blocks, the Injector Drive Laser, Sector 20 Laser Facility and a Magnetic Measurement Facility (complete with measurement and fiducialization equipment) were all procured in 2006. In addition, there were several refurbishment projects to prepare the SLAC site for the LCLS. These included the S24 stairway upgrade, BSY vertical wall upgrade, FFTB equipment and shielding removal, and excavation of activated soil in preparation for the start of LCLS construction in September 2006.

The LCLS project reports monthly performance, variances and contingency allocation against an approved baseline. Configuration management is in place which complies with DOE O 413.3. Monthly performance status is reported to DOE via the Project Assessment and Reporting System (PARS). LCLS conducted an Earned-Value Management System (EVMS) review with DOE’s Office of Engineering, Construction and Management in order to validate the LCLS EVMS.

LCLS Scientific/Technical Progress – For 2006, the LCLS is primarily a ‘design-procureconstruct’ project and has passed the 30% completion point. The Architect/Engineer has submitted the Title-II design package to SLAC for review at the “100% of Complete” stage. LCLS has contracted with a Construction Manager/General Contractor (CM/GC) who will prepare the construction bid packages and contract with trade contractors to build the LCLS civil construction. All bid packages for the LCLS have been solicited and approximately 70% have been awarded. LCLS has taken ‘beneficial occupancy’ of the Sector 20 Laser Facility and the Magnetic Measurement Facility.

For the main construction effort, SLAC-LCLS has cleared the Research Yard for the start of the main construction effort. This included the FFTB equipment removal and shielding, demolition of B113 and partial demolition of B102. A number of utilities were also removed or rerouted. In September 2006, the CM/GC has begun the main LCLS construction effort.

LCLS has also begun installing the Injector and Linac beamlines and the Injector beam commissioning will begin early in 2007. The LCLS Drive Laser has been installed in the Sector 20 Laser Facility and preliminary commissioning activities are underway. The LCLS RF Gun has been fabricated and is now in final assembly and test. The new X-band klystron was tested at >50 MW with no performance problems identified. RF gun solenoid magnetic measurements are in progress, as are many of the LCLS 135 MeV injector beamline components.

The 2006 shutdown is under way during which installation is occurring of a large portion of the LCLS Injector beamline in SLAC’s Linac and the LCLS Injector enclosures. At the completion of the installation, LCLS will begin preparing the LCLS Injector for commissioning.

Undulator production is under way using two undulator assembly vendors each of whom is approved to proceed with the assembly of undulators 3-16. At the end of 2006, a total of 12 undulators (30%) have been completed. The first production undulator has been acceptance tested and pretuned (Keff set) on the Dover measurement bench in SLAC’s Magnetic Measurement Facility (MMF).

A Single Undulator Test (SUT) was constructed at ANL, consisting of an integrated undulator system module from the floor up to verify undulator system and performance measurement. The SUT successfully tested all motion control and performance criteria against the physics requirements.

A prototype rf beam position monitor (BPM) has been installed in the ANL injector test stand and has undergone a series of beam tests. Although tests are not complete, a significant amount of information has been obtained and the design appears robust.

For LCLS photon systems, several new staff members have been added to the XTOD and XES teams. Prototypes of both the gas and solid attenuator systems have been developed that meet the physics requirements of the LCLS. LCLS-TN-06-1 "The Physics Analysis of a Gas Attenuator with Argon as a Working Gas,” describes the use of argon gas to extend the gas attenuation for photon energies up to 8 keV. A “prototype” has been constructed with 3 small chambers, orifices, and data acquisition system to experimentally verify the pressure calculations. The design goal of 20-torr operation was met with stable operation with boil-off nitrogen up to a pressure of 60 torr observed. The measured pressure distribution and required gas flow are in good agreement with calculation.

The conceptual design of the X-ray slit subsystem has been developed. It is more compact than the previous design and has very few parts in the vacuum. Investigation into the feasibility of making the slit blocks as desired has begun. Thus far, they appear to be feasible to manufacture as conceived.

The XTOD group conducted damage experiments measuring the depths of any craters observed. The gas detector data from TTF provided measured fluence for each sample shot during the damage experiment. Clear correlation between the crater depths measured on the SiC sample with the gas detector fluences was observed. Pulse-to-pulse fluence was found to vary by 200% (lowest to highest). Applying the model to our single shot data taken at lower fluences has shown the damage threshold for SiC to be at about the melt dose which is consistent with expectations and indicates that these materials will perform under design conditions in the LCLS beam.

For the FEL Offset Mirror System, calculations were performed of the predicted FEL characteristics after reflection from state-of-the-art X-ray mirrors. The calculations predict some broadening of the FEL beam after reflection from mirrors of these types. A set of specifications consistent with this performance is being prepared for use in obtaining vendor quotes and developing physics requirements for the mirrors.

Cornell University is collaborating on the LCLS 2D detector project as this project ramps up during its second year.

The experimental capabilities desired by the AMO group have been substantially defined: a chamber with a pulsed or continuous gas jet, with multiple electron time-of-flight spectrometers, ion spectrometer for charge state determination and ion imagining, and one or two X-ray fluorescence spectrometers.

Detailed information on the Project status and issues may be found in the Monthly Reports, posted at http://www-ssrl.slac.stanford.edu/lcls/internals/monthlyreports/.


- Top -
Last update: 11/03/2008