Final Survey
(Final Ring Alignment)
Scheduled Milestones
(Rev. 11.35)
|
Expected Start Date October 22, 2003 |
Expected End Date October 30, 2003 |
|
|
START DATE |
END DATE |
DETAILS |
Activity ID |
| Oct 15, 2003 | Oct 25, 2003 | Alignment mapping preparation * |
AL0504 |
| Oct 22, 2003 | Oct 30, 2003 | Magnets & Vacuum Final alignment | IN9270 |
|
* delays in the installation of straight section and girder bellows created the opportunity to add this task to facilitate the mapping of the vacuum chambers |