Front End Alignment
Scheduled Milestones
(Rev. 11.35)
|
Expected Start Date September 5, 2003 |
Expected End Date October 17, 2003 |
|
|
START DATE |
END DATE |
DETAILS |
Activity ID |
| Sep 19, 2003 | Sep 22, 2003 | Align BL3 Front End | VS0320 |
| Sep 19, 2003 | Sep 22, 2003 | Align BL4 Front End | VS0345 |
| Sep 23, 2003 | Sep 23, 2003 | Align BL11 Front End | VS0370 |
| Sep 5, 2003 | Sep 8, 2003 | Align BL6 Front End | VS0395 |
| Sep 22, 2003 | Sep 23, 2003 | Align BL5 Front End | VS0420 |
| Oct 3, 2003 | Oct 3, 2003 | Align BL1 Front End | VS0445 |
| Oct 16, 2003 | Oct 17, 2003 | Align BL2 Front End | VS0470 |
| Oct 16, 2003 | Oct 17, 2003 | Align BL7 Front End | VS0495 |
| Sep 9, 2003 | Sep 10, 2003 | Align BL8 Front End | VS0520 |
| Oct 1, 2003 | Oct 2, 2003 | Align BL9 Front End | VS0545 |
| Oct 2, 2003 | Oct 3, 2003 | Align BL10 Front End | VS0670 |
|
|