Activity ID
Jul 1, 2003 Jul 2, 2003 Mark floor G12 ST0105
Jul 1, 2003 Jul 2, 2003 Mark floor G13 & S12 ST0110
Jul 2, 2003 Jul 3, 2003 Mark floor G11 & S10 ST0115
Jul 2, 2003 Jul 3, 2003 Mark floor G14 & S13 ST0120
Jul 3, 2003 Jul 7, 2003 Mark floor G10 & S9 & ISO valve ST0125
Jul 3, 2003 Jul 7, 2003 Mark floor G15 & S14 ST0130
Jul 7, 2003 Jul 8, 2003 Mark floor G9 & S8 ST0135
Jul 7, 2003 Jul 8, 2003 Mark floor G16 & S15 ST0140
Jul 8, 2003 Jul 9, 2003 Mark floor G8 & S7 ST0145
Jul 8, 2003 Jul 9, 2003 Mark floor G17 & S16 ST0150
Jul 9, 2003 Jul 10, 2003 Mark floor G7 & S6 ST0155
Jul 9, 2003 Jul 10, 2003 Mark floor G18 & S17 ST0160
Jul 10, 2003 Jul 11, 2003 Mark floor G6 & S5 ST0165
Jul 10, 2003 Jul 11, 2003 Mark floor G1 & S18 & ISO valve ST0170
Jul 11, 2003 Jul 14, 2003 Mark floor G5 & S4 ST0175
Jul 11, 2003 Jul 14, 2003 Mark floor G2 & S1 ST0180
Jul 14, 2003 Jul 15, 2003 Mark floor G4 & S3 ST0185
Jul 14, 2003 Jul 15, 2003 Mark floor G3 & S2 ST0190