Monumentation
(Network Installation & Control)
Scheduled Milestones
(Rev. 11.35)
|
Expected Start Date June 23, 2003 |
Expected End Date July 25, 2003 |
|
|
START DATE |
END DATE |
DETAILS |
Activity ID |
| Jun 23, 2003 | Jun 25, 2003 | Install new monumentation in SPEAR ring | AL0110 |
| Jun 25, 2003 | Jul 1, 2003 | Survey ring and beamline monumentation | AL0120 |
| Jul 21, 2003 | Jul 25, 2003 | Control network | AL0360 |
Note: Fiducialization of BTS quads Q6 and Q7 are scheduled to take
place from about June 26th to July 1st . The laser tracker will be used
for fiducialization after these magnets have already been placed into their
final position. See
|