Expected Start Date
June 23, 2003
Expected End Date
July 25, 2003

Overview

START DATE
END DATE
DETAILS
Activity ID
Jun 23, 2003 Jun 25, 2003 Install new monumentation in SPEAR ring AL0110
Jun 25, 2003 Jul 1, 2003 Survey ring and beamline monumentation AL0120
Jul 21, 2003 Jul 25, 2003 Control network AL0360


= task completed

Note: Fiducialization of BTS quads Q6 and Q7 are scheduled to take place from about June 26th to July 1st . The laser tracker will be used for fiducialization after these magnets have already been placed into their final position. See Miscellaneous Ring Alignment details for more information.