Metrology Department
 

Monumentation


Detailed Schedule

Overview:
New monumentation is necessary on all portions of the new concrete floor. These points will be established with respect to the remaining SPEAR2 monuments which are the 3D points located in the long straights area and in the SSRL buildings:

          http://www-group.slac.stanford.edu/met/Align/TechAnalysis/2003/SPEAR3_Datum.pdf





Details:
The first task is the installation of floor monuments into the newly poured concrete floor as well as leveling rivets around the ring. All these points will be positioned according to the simulation results. A global survey of all these new points and all wall, ring and SSRL points will include laser tracker triplets and automatic level height differences. Next a temporary set of coordinates will be established and used for setting the templates. Because of the short period of time from the completion of the concrete floor, another global survey will be performed to control the network and allow the generation of final coordinates for SPEAR3.


Contact:
Catherine  Le Cocq

- Top -
Last update: April 12, 2007