A laser scan survey of the LCLS facility began in August 2008. A laser scan of the LCLS beamline will be made ranging from the photo-injector (Sector 20 in the linac) through to the Far Experimental Hall (FEH).

Access Schedule (2008)

Region

Downtime Week

 Dates

Business Days

 Area Manager

Linac

 1, 2, 3

 Aug. 21 to  Sept.  5

 11

 Tom Graul

BSY

 4, 5

 Sept.  8  to  Sept.19

 10

 Al Baker

Injector

 6, 7

 Sept. 22 to  Oct.   3

 10

 Patrick Smith

 

 

 

 

 

 