Metrology Department
 

Miscellaneous Alignment



Scheduled Milestones
(Rev. 11.35)
Expected Start Date
May 13, 2003
Expected End Date
June 25, 2003

Overview

START DATE
END DATE
DETAILS
Activity ID
May 13, 2003 May 19, 2003 Align BL4 Insertion Device Chamber ID0160
June 4, 2003 June 5, 2003 (Delayed: See Ringwall or Rolling 6-week Look Ahead Schedule) ID0160
May 14, 2003 May 20, 2003 Align BL7 Insertion Device Chamber ID0240
June 10, 2003 June 11, 2003 (Delayed: See Ringwall or Rolling 6-week Look Ahead Schedule) ID0240
Jun 19, 2003 Jun 25, 2003 Align BL6 Insertion Device Chamber ID0295
Aug 7, 2003 Aug 8, 2003 (Delayed: See Ringwall or Rolling 6-week Look Ahead Schedule) ID0295
Oct   2003 ? Nov   2003 ? (Delayed: Should be measured before Nov 4; See Rolling 6-week Look Ahead Schedule) ID0295

= task completed


- Top -
Last update: April 13, 2007