Miscellaneous Alignment
Scheduled Milestones
(Rev. 11.35)
|
Expected Start Date May 13, 2003 |
Expected End Date June 25, 2003 |
|
|
START DATE |
END DATE |
DETAILS |
Activity ID |
| May 13, 2003 | May 19, 2003 | Align BL4 Insertion Device Chamber | ID0160 |
| June 4, 2003 | June 5, 2003 | (Delayed: See Ringwall or Rolling 6-week Look Ahead Schedule) | ID0160 |
| May 14, 2003 | May 20, 2003 | Align BL7 Insertion Device Chamber | ID0240 |
| June 10, 2003 | June 11, 2003 | (Delayed: See Ringwall or Rolling 6-week Look Ahead Schedule) | ID0240 |
| Jun 19, 2003 | Jun 25, 2003 | Align BL6 Insertion Device Chamber | ID0295 |
| Aug 7, 2003 | Aug 8, 2003 | (Delayed: See Ringwall or Rolling 6-week Look Ahead Schedule) | ID0295 |
| Oct 2003 ? | Nov 2003 ? | (Delayed: Should be measured before Nov 4; See Rolling 6-week Look Ahead Schedule) | ID0295 |
|
|