Miscellaneous Ring Alignment
Scheduled Milestones
(Rev. 11.35)
|
Expected Start Date June 26, 2003 |
Expected End Date September 15, 2003 |
|
|
START DATE |
END DATE |
DETAILS |
Activity ID |
| Jun 26, 2003 | Jul 1, 2003 | In situ fiducialization of BTS Quads Q6 & Q7 | N/A |
| Sep 9, 2003 | Sep 10, 2003 | Align new BTS Raft | IN0456 |
| Sep 11, 2003 | Sep 15, 2003 | Align Cavities | IN1110 |
|
|