Metrology Department
 

Straight Section Alignment



Scheduled Milestones
(Rev. 11.35)
Expected Start Date
August 20, 2003
Expected End Date
September 9, 2003

Overview

START DATE
END DATE
DETAILS
Activity ID
Aug 20, 2003 Aug 21, 2003 Quadrant 3 - S10 (Spool) Straights Align AL0415
Aug 21, 2003 Aug 22, 2003 Quadrant 3 - S11 (BL6 ID) Straights Align AL0420
Aug 22, 2003 Aug 25, 2003 Quadrant 3 - S12 (BL5 ID) Straights Align AL0425
Aug 25, 2003 Aug 26, 2003 Quadrant 3 - S13 (BL4 ID) Straights Align AL0430
Aug 29, 2003 Sep 2, 2003 West - S18 non-RF Vac Components Align AL0435
Aug 27, 2003 Aug 28, 2003 Quadrant 4 - S14 (Spool/valve) Straights Align AL0440
Aug 28, 2003 Aug 29, 2003 Quadrant 4 - S15 (BL11 ID) Straights Align AL0445
Aug 29, 2003 Sep 2, 2003 Quadrant 4 - S16 (Spool) Straights Align AL0450
Sep 2, 2003 Sep 3, 2003 Quadrant 4 - S17 (Spool) Straights Align AL0455
Sep 3, 2003 Sep 3, 2003 Quadrant 1 - S1 (Diagnostics) Straights Align AL0460
Sep 4, 2003 Sep 4, 2003 Quadrant 1 - S2 (Kicker) Straights Align AL0465
Sep 5, 2003 Sep 8, 2003 Quadrant 1 - S3 (Septum) Straights Align AL0470
Sep 8, 2003 Sep 9, 2003 Quadrant 1 - S4 (Kicker/valve) Straights Align AL0475
Aug 25, 2003 Aug 25, 2003 Quadrant 2 - S5 (BL7 ID) Straights Align AL0480
Aug 26, 2003 Aug 26, 2003 Quadrant 2 - S6 (BL10 ID) Straights Align AL0485
Aug 27, 2003 Aug 27, 2003 Quadrant 2 - S7 (BL9 ID) Straights Align AL0490
Aug 28, 2003 Aug 28, 2003 Quadrant 2 - S8 (Spool) Straights Align AL0495
Aug 21, 2003 Aug 22, 2003 East - S9 (Spool) Straights Align AL0500


= task completed


- Top -
Last update: April 13, 2007