Bend Magnet Beamline Alignment



 
Work Week
April 14 To April 20
 



Date Crew Summary Photo
4/15 Imfeld
McDougal
Perry
 
Checked monumentation in BL1
Surveyed 1 plug in BL7 for datum check
 
4/16 Banuelos
Imfeld
McDougal
Perry
 
Installed 3 new plugs for BL1
Installed 4 new plugs for BL2
Installed 4 new plugs for BL8
4/17 Imfeld
Perry
 
Installed 5 new plugs for BL3  