Date Crew Summary Photo
12/1 Griffin
Imfeld
 
Mapped 1S components and flanges with TC2002  
12/1 Gaudreault
Rogers
 
BTS: Added 3 wall monuments to survey Q5 and Q6  
12/2 Gaudreault
Rogers
 
BTS: Surveyed newly installed monuments  
12/3 Gaudreault
Imfeld
McDougal
 
BTS line: Alignment of pipe  
12/4 Imfeld
Rogers
 
BTS: Moved Q5 and Q6
12/4 Gaudreault
McDougal
 
BTS line: Alignment of pipe and flanges
12/5 Gaudreault
Rogers
 
BTS line: Moved profile monitor number 2 in X to match the pipe flange  