11/17 Banuelos
Imfeld
Juarez
Rogers
 
Set some components on SC16 and SC17
11/17 Gaudreault
Griffin
Juarez
 
Moved components on SC15
11/18 Gaudreault
Juarez
Rogers
 
Finished setting SC15 started SC2  
11/18 Gaydosh
Griffin
Imfeld
 
Set components on SC17 and SC18
11/18 Banuelos
McDougal
Perry
 
Finshed setting SC16, started on SC4  
11/19 Banuelos
McDougal
Perry
 
Finished SC1, moved most components on SC3  
11/19 Gaudreault
Juarez
Rogers
 
Finished setting SC2, set SC4 and SC5
11/19 Gaydosh
Griffin
Imfeld
 
Moved components on SC1  
11/20 Fuss
Gaydosh
 
Develop tracker observation procedure to measure X and Y on vacuum chambers using a 20 inch extension bar
11/20 Griffin
Imfeld
 
SC07  
11/20 Gaudreault
Juarez
Rogers
 
Magnet moves  
11/21 Fuss
Gaydosh
LeCocq
 
Read and moved vacuum chambers in zones 1 and 2 using spherical arcing
Note: Click on camera icon for three mini-movies of this technique
11/21 Gaudreault
Juarez
Rogers
 
Align magnets  
11/21 Griffin
Imfeld
 
SC12  
11/22 Gaudreault
Griffin
Imfeld
Juarez
McDougal
Perry
Rogers
 
Finished reading and moving magnets and vacuum chambers (in elevation only)  
11/22 Fuss
Gaydosh
LeCocq
 
Read and moved vacuum chambers in zones 2, 4 and 5  
11/23 Fuss
Gaudreault
Gaydosh
LeCocq
 
Finished moving vacuum chambers (zone 3)
Note: Click on camera icon for November vacuum chamber position results and mini-movies of the measuring technique
Activity IN9270 completed.