Miscellaneous Ring Alignment
| Work Week November 17 To November 23 |
| Date | Crew | Summary | Photo |
|---|---|---|---|
| 11/17 | McDougal Perry |
Re-set part of BL6 | |
| 11/20 | McDougal Perry |
Reset roll after vacuum repair in BL4 | |
| 11/22 | McDougal Perry |
BL6 ID chamber versus gap opening | |
| 11/22 | McDougal Perry |
Read 1S components | |
| 11/22 | Gaudreault Juarez Rogers |
BTS: set pipe downstream after addition of new support | |
| 11/23 | Fuss Gaudreault |
BTS check pipe at raft exit |