Straight Section Alignment
| |
|
Work Week
November 10 To November 16 |
|
|
| Date |
Crew |
Summary |
Photo |
| 11/10 |
McDougal Perry |
Set 1S downstream |
|
| 11/11 |
McDougal Perry |
Set 10S downstream and 1S
upstream (DCCT still missing) |
|
| 11/12 |
McDougal Perry |
Checked 1S DS after swapping bolt |
|
| 11/13 |
McDougal Perry |
Set BL6 ID
Activity AL0420 completed. |
|
| 11/14 |
Fuss Gaudreault Griffin |
Set 10S upstream chamber for
placement of bellows
Activity AL0415 completed. |
|
| 11/15 |
Imfeld Perry |
Checked 1S fully installed
Activity AL0460 completed. |
|
|