Metrology Department
 

Straight Section Alignment



 
Work Week
November 3 To November 9
 



Date Crew Summary Photo
11/3 McDougal
Perry
Rogers
 
Set BL5 ID  
11/4 McDougal
Perry
Rogers
 
Set BL5 ID and finished 8S
Activity AL0495 completed.
11/5 McDougal
Perry
 
Set 9-1 & 17S  
11/7 McDougal
Perry
 
Set 9S (9S-1, 9S-2 and 9S valve)
Activity AL0500 completed.
 
11/8 Imfeld
Perry
 
Set 14S and 18S valves
Activities AL0435 & AL0440 completed.
 