Metrology Department
 

Miscellaneous Ring Alignment



 
Work Week
October 27 To November 2
 



Date Crew Summary Photo
10/30 Banuelos
Gaudreault
 
Started alignment of BTS parts between vertical bend & septum
10/31 Banuelos
Gaudreault
 
Set BTS profile monitor  
11/1 Gaudreault
Perry
 
Checked BTS profile monitor and DS tube  