Metrology Department
 

Front End Alignment



 
Work Week
October 27 To November 2
 



Date Crew Summary Photo
10/27 Griffin
McDougal
 
BL3: Started setting separation chamber and mask tank was moved to install plug  
10/28 Griffin
McDougal
 
BL3: Continued with separation chamber and mask tank
10/31 Griffin
McDougal
 
BL3: Finished separation chamber and mask tank  

- Top -
Last update: April 11, 2007