Metrology Department
 

Miscellaneous Ring Alignment



 
Work Week
October 6 To October 12
 



Date Crew Summary Photo
10/6 Griffin
McDougal
 
Checked flanges on cell 13. Moved DS BM2 40 mil in X
10/7 Griffin
McDougal
 
Checked flanges on cell 18. Moved DS BM2 58 mils in X and US BM1 48 mils in X  

- Top -