Metrology Department
 

Miscellaneous Alignment



 
Work Week
September 22 To September 28
 



Date Crew Summary Photo
9/22 Griffin
McDougal
 
SLAC Vacuum : Started fiducializing BL1 fixed mask  
9/23 Griffin
McDougal
 
SLAC Vacuum : Finished fiducializing BL1 fixed mask  
9/24 Griffin
McDougal
 
SLAC Vacuum : Check roll on DCCT chamber and rework BL1 fixed mask (leak)  
9/25 Griffin
McDougal
 
SLAC Vacuum : Finished rework of BL1 fixed mask  
9/26 Gaydosh
Griffin
McDougal
 
Bld 31: Fiducialized 1 elliptical chamber and 1 cam chamber (noticed then that 3 TBs were missing)  