| Date |
Crew |
Summary |
Photo |
| 9/8 |
Griffin Rogers |
SSRL Vacuum: Worked on K1 raft |
|
| 9/9 |
Griffin Rogers |
SSRL Vacuum: Finished K1 raft and
started K3 raft |
|
| 9/10 |
Griffin Rogers |
SSRL Vacuum: Worked on K3 raft |
|
| 9/11 |
Griffin Rogers |
SSRL Vacuum: Finished kicker 3
raft and started fiducializing SLM absorber |
|
| 9/12 |
Griffin Rogers |
SSRL Vacuum : Finished
fiducializing SLM Absorber |
|
| 9/12 |
Gaudreault Imfeld |
Bld 31: Prepared for QC of
straight section chamber also called elliptical
chambers |
|