Miscellaneous Ring Alignment
| |
|
Work Week
September 8 To September 14 |
|
|
| Date |
Crew |
Summary |
Photo |
| 9/8 |
Imfeld McDougal Perry |
Set elevations for RF cavities
1-3 |
|
| 9/9 |
Imfeld McDougal Perry |
Aligned the 4 RF cavities
Activity IN1110 completed. |
|
| 9/9 |
Gaudreault Imfeld |
Mapped quad positions near IDs in
the north arc |
|
| 9/11 |
Gaudreault Imfeld |
Map end quads on cells (between
straights) |
|
|