Miscellaneous Alignment
| |
|
Work Week
September 1 To September 7 |
|
|
| Date |
Crew |
Summary |
Photo |
| 9/2 |
Griffin Rogers |
SSRL Vacuum: Fiducilized BL6-2
photon BPM |
|
| 9/2 |
Banuelos Gaudreault |
SSRL Vacuum: Assembled K2 with
its upbeam part Worked on K3 raft to
straighten upbeam part for welding |
|
| 9/3 |
Griffin McDougal |
SSRL Vacuum: Worked on K1 raft |
|
| 9/3 |
Banuelos Gaudreault |
Bld 750: Alignment of the K2 with
the septum chamber |
|
|