Metrology Department
 

Miscellaneous Alignment



 
Work Week
August 25 To August 31
 



Date Crew Summary Photo
8/25 Gaudreault
Rogers
 
SSRL Vacuum: Checked parallism of flanges on upbeam part of K2  
8/26 Gaudreault
Rogers
 
SSRL Vacuum: BL9 beryllium window & graphite filter alignment
8/27 Gaudreault
Rogers
 
SSRL Vacuum: Finished shooting graphite filter for BL9-0  
8/28 Gaudreault
Griffin
Rogers
 
SSRL Vacuum: Worked on K3 assembly raft
Downbeam part completed to K3; still need upbeam part assembled
 
8/29 Gaudreault
Griffin
 
Bld 750: Set chamber in septum