Metrology Department
 

Miscellaneous Alignment



 
Work Week
August 18 To August 24
 



Date Crew Summary Photo
8/18 Carrillo
Gaudreault
 
SSRL Vacuum: Started fiducialization of upbeam mask for K1 assembly  
8/18 Carrillo
Gaudreault
 
Building 26: Calibrate counter BL4 ID  
8/19 Carrillo
Gaudreault
 
SSRL Vacuum: Finished fiducializing upbeam mask for K1. Worked on K1 raft after RF seals installed  
8/20 Carrillo
Gaudreault
 
SSRL Vacuum: RF seals installed in K1 assembly; aligned assembly to raft  
8/21 Carrillo
Gaudreault
 
SSRL Vacuum: Monitored welding on K2 kicker  
8/21 Banuelos
Imfeld
 
Bld 750: Set septum magnet on stand
8/22 Carrillo
Gaudreault
 
SSRL Vacuum: Flanges checked on kicker 2

- Top -
Last update: April 11, 2007