Front End Alignment
| |
|
Work Week
August 18 To August 24 |
|
|
| Date |
Crew |
Summary |
Photo |
| 8/18 |
McDougal Perry |
BL2 in-alcove alignment,
injection stopper, graphite filter, Beryllium
window assembly |
|
| 8/20 |
McDougal Perry |
BL8 in-alcove alignment, 8-1 M0
mirror, cold finger box, injection stopper reset
BL6 injection stopper |
|
| 8/21 |
McDougal Perry |
BL7 injection stopper BL8 cold
finger allocation box BL10 rough align
injection stopper |
|
| 8/22 |
McDougal Perry |
BLs 9 & 10 injection stopper
final BL4 injection stopper rough check for
shim |
|
|