Date Crew Summary Photo
8/11 Carrillo
Gaudreault
Griffin
Rogers
 
SSRL Vacuum: Finished BL4 stopper to collimator and BL11 stopper to collimator. Fiducialized kicker 3
8/12 Carrillo
Imfeld
 
SSRL Vacuum: Initial assembly of kicker 3
8/12 Gaudreault
Griffin
Rogers
 
SSRL Vacuum: Re-did BL11 fixed mask to moveable mask tank (had a leak)
8/12 Gaudreault
Griffin
Rogers
 
SSRL Vacuum: Fiducialized BL7 stopper tank and set collimator to tank
8/13 Carrillo
Gaudreault
Imfeld
 
SSRL Vacuum: Final assembly of K3/4S
8/13 Gaudreault
Griffin
Rogers
 
SSRL Vacuum: Checked fiducialization on BL7 stopper tank after welding. Started BL7 moveable mask to fixed mask (redo - had a vacuum leak)
8/14 Carrillo
Gaudreault
 
SSRL Vacuum: Refiducialized kicker 1 and started straight assembly of kicker 1 raft  
8/15 McDougal
Perry
 
Building 31: Fiducialized septum vacuum chamber  
8/15 Carrillo
Gaudreault
 
SSRL Vacuum: Worked on K1 raft assembly. Refiducialized downbeam K1 SN01  