Date Crew Summary Photo
8/4 Griffin
Rogers
 
SSRL Vacuum: Started BL4 stopper  
8/5 Imfeld
Juarez
 
SSRL Vacuum: Prepared kicker 1 assembly  
8/5 Griffin
Rogers
 
SSRL Vacuum: BL4 stopper and started fiducialzing BL4 pre-mask  
8/6 Imfeld
Juarez
 
SSRL Vacuum: Found flanges of kicker 1 out of tolerance (10 mrad pitch). Need re-machining  
8/6 Griffin
Rogers
 
SSRL Vacuum: Finished fiducializing BL5 pre-mask, started setting fixed and pre-mask to moveable mask tank  
8/7 Griffin
Rogers
 
SSRL Vacuum: Finished setting BL5 fixed and pre-mask to moveable mask tank. Refid. BL9 stopper tank
8/8 Banuelos
Carrillo
Gaudreault
Juarez
Perry
Rogers
 
SSRL Vacuum: BL9 fixed mask to moveable mask, (redo) BL9 injection stopper to collimator, BL7 stopper
8/9 Carrillo
Perry
 
SSRL Vacuum: Worked on BL4, BL7 and BL11 stopper tanks  