| Date |
Crew |
Summary |
Photo |
| 8/4 |
Griffin Rogers |
SSRL Vacuum: Started BL4 stopper |
|
| 8/5 |
Imfeld Juarez |
SSRL Vacuum: Prepared kicker 1
assembly |
|
| 8/5 |
Griffin Rogers |
SSRL Vacuum: BL4 stopper and
started fiducialzing BL4 pre-mask |
|
| 8/6 |
Imfeld Juarez |
SSRL Vacuum: Found flanges of
kicker 1 out of tolerance (10 mrad pitch). Need
re-machining |
|
| 8/6 |
Griffin Rogers |
SSRL Vacuum: Finished
fiducializing BL5 pre-mask, started setting
fixed and pre-mask to moveable mask tank |
|
| 8/7 |
Griffin Rogers |
SSRL Vacuum: Finished setting BL5
fixed and pre-mask to moveable mask tank. Refid.
BL9 stopper tank |
|
| 8/8 |
Banuelos Carrillo
Gaudreault Juarez Perry Rogers |
SSRL Vacuum: BL9 fixed mask to
moveable mask, (redo) BL9 injection stopper to
collimator, BL7 stopper |
|
| 8/9 |
Carrillo Perry |
SSRL Vacuum: Worked on BL4, BL7
and BL11 stopper tanks |
|