Metrology Department
 

Miscellaneous Ring Alignment



 
Work Week
August 4 To August 10
 



Date Crew Summary Photo
8/6 Banuelos
Perry
 
Preliminary in-alcove alignment on BL8: set 8-1 M0, set shim heights for stopper tank, measured existing components  
8/7 Banuelos
Perry
 
BL8 in-alcove alignment
8/7 Carrillo
Gaudreault
 
Set BTS caps in elevation before grouting
8/8 Carrillo
Gaudreault
 
Set plates for BL10 ID device