Metrology Department
 

Support Plate Alignment



 
Work Week
July 28 To August 3
 



Date Crew Summary Photo
7/28 Imfeld
 
Mapped plates from cell 4 to to cell 1
7/28 Banuelos
Carrillo
Gaudreault
Perry
 
G16: 1 cell plate
S16: 2 straight plates
G17: 6 cell plates
S17: 2 straight cells
G18: 6 cell plates
Activities AL0665 & AL0670 completed.
 
7/29 Banuelos
Carrillo
Gaudreault
Imfeld
McDougal
Perry
 
Adjusted SLM plates and flagged mapped plates
S14: 2 straight plates
G15: 6 cell plates
G16: 5 cell plates
S18: 4 RF cavities & 1 ISO plates
Activities AL0655, AL0675 & AL0680 completed.
7/30 Banuelos
Gaudreault
McDougal
Surbaugh
 
G14: 5 cell plates
G13: 6 cell plates
Adjusted flagged mapped plates in G18
Activity AL0685 completed.
 
7/30 Imfeld
 
Mapped plates in cells 1, 18 and 17
7/31 Banuelos
Surbaugh
 
Mapped plates from cell 17 to cell 13
7/31 Carrillo
Gaudreault
 
G14: 1 cell plate
G12: 6 cell plates
Adjusted flagged mapped plates in G15
Activities AL0605 & AL0690 completed.
 
8/1 Imfeld
Surbaugh
 
Mapped cell 11 to check before and after grouting  
8/1 Banuelos
Carrillo
 
Mapped cell 13 & cell 12
All support plate activities fully completed.
 

- Top -
Last update: April 11, 2007