Metrology Department
 

Miscellaneous Alignment



 
Work Week
July 21 To July 27
 



Date Crew Summary Photo
7/21 Griffin
Rogers
 
SSRL Vacuum: Worked on BL2 collimator and BL10 fixed mask  
7/22 Griffin
Rogers
 
SSRL Vacuum: Finished setting BL6 fixed mask to moveable mask tank and worked on BL3 and BL2 collimators
7/22 Gaudreault
Juarez
 
Bld 26: Worked on septum magnet and wire  
7/23 Griffin
Rogers
 
SSRL Vacuum: Refiducialized BL6 Stopper using 1" TBs  
7/23 Griffin
Rogers
 
SSRL Vacuum: Finished setting BL2 & 3 Collimators to Stoppers
7/24 Rogers
 
SSRL Vacuum: Set BL6 collimator to stopper and set BL4 fixed mmask to moveable mask  
7/25 Griffin
Rogers
 
SSRL Vacuum: Set BL7 & 9 fixed mask to moveable mask and started fiducializing BL8 cold finger / allocation mask  
7/25 Gaudreault
Juarez
 
Bld 750: Moved chamber on raft 81according to new fiducials  