Metrology Department
 

Support Plate Alignment



 
Work Week
July 21 To July 27
 



Date Crew Summary Photo
7/21 Carrillo
Gaudreault
Imfeld
McDougal
Perry
 
G8: 2 cell plates
S8: 1 straight plate
S9: 3 straight plates
S10: 2 straight plates
G11: 4 cell plates
Activity AL0610 completed.
7/22 Banuelos
Carrillo
Gaudreault
Imfeld
McDougal
Perry
 
G5: 4 cell plates
G6: 6 cell plates
G7: 6 cell plates
G8: 4 cell plates
S8: 1 straight plate
S9: 1 straight & 1 ISO plate
Activities AL0615, AL0620, AL0625, AL0630 & AL0635 completed.
7/23 Banuelos
Carrillo
McDougal
Perry
 
G1: 2 cell plates
G3: 6 cell plates
S4: 2 straight plates
G5: 2 cell plates
Activity AL0640 completed.
7/23 Gaudreault
Imfeld
LeCocq
 
Mapped plates from cell 11 to cell 8
7/24 Banuelos
Carrillo
McDougal
Perry
 
G1: 4 cell plates
S1: 1 straight plate
G2: 1 cell plate
S2: 1 straight plate
G4: 6 cell plates
 
7/24 Gaudreault
Imfeld
 
Mapped plates from cell 8 to cell 4
7/25 Carrillo
Gaudreault
Juarez
Perry
 
S1: 1 straight plate
G2: 5 cell plates
S2: 1 straight plate
S3: 1 straight plate for septum
Activities AL0645, AL0650 & AL0660 completed.
 
7/25 Banuelos
Imfeld
 
Set SLM (BL0) plates

- Top -