| Date |
Crew |
Summary |
Photo |
| 7/14 |
Perry Rogers |
Precise level control network in
Q3 & Q4 |
|
| 7/14 |
Banuelos Carrillo |
Laser tracker #98 control network
in Q2 |
|
| 7/14 |
Gaudreault Surbaugh |
Laser tracker #18 control network
in Q4 |
|
| 7/15 |
McDougal Perry |
Precise level control network in
Q1 & Q2 |
|
| 7/15 |
Banuelos Carrillo |
Laser tracker #98 control network
in Q1 |
|
| 7/15 |
Gaudreault Surbaugh |
Laser tracker #18 control network
in Q3 |
|
| 7/16 |
Gaudreault Perry |
Precise level control network in
west straight (densify) |
|
| 7/16 |
Banuelos Carrillo |
Finished laser tracker survey in
Q1 Networking activity
AL0360 completed. |
|