| Date |
Crew |
Summary |
Photo |
| 6/16 |
Carrillo Perry |
Moved monuments for rebar in Q2
and Q3. Initial marking of monuments in Q4 |
|
| 6/17 |
Carrillo Perry |
Finished pre-marking Q4 monument
positions |
|
| 6/18 |
Imfeld McDougal |
Staged and calibrated three sets
of tracker gear |
|
| 6/18 |
Carrillo Perry |
Drilled monuments in the
following areas: Q2, Q3, and Q4 |
|
| 6/19 |
Carrillo Gaudreault Juarez |
Laser tracker network west side
of ring. Septum |
|
| 6/19 |
Carrillo Imfeld |
Collected tracker data for
monumentation survey in west sections |
|
| 6/19 |
McDougal Perry |
Installation of
monumentation (Activity AL0110) completed
including Q1. |
|
| 6/20 |
Carrillo Gaudreault |
Laser tracker network (south arc
of ring) |
|
| 6/21 |
Gaudreault Juarez |
Levels for network (ending west
straight region) |
|
| 6/21 |
Banuelos Imfeld |
Collected tracker data for
monumentation survey (Q1) |
|