Metrology Department
 

Monumentation



 
Work Week
June 16 To June 22
 



Date Crew Summary Photo
6/16 Carrillo
Perry
 
Moved monuments for rebar in Q2 and Q3. Initial marking of monuments in Q4
6/17 Carrillo
Perry
 
Finished pre-marking Q4 monument positions
6/18 Imfeld
McDougal
 
Staged and calibrated three sets of tracker gear
6/18 Carrillo
Perry
 
Drilled monuments in the following areas: Q2, Q3, and Q4
6/19 Carrillo
Gaudreault
Juarez
 
Laser tracker network west side of ring. Septum  
6/19 Carrillo
Imfeld
 
Collected tracker data for monumentation survey in west sections
6/19 McDougal
Perry
 
Installation of monumentation (Activity AL0110) completed including Q1.  
6/20 Carrillo
Gaudreault
 
Laser tracker network (south arc of ring)
6/21 Gaudreault
Juarez
 
Levels for network (ending west straight region)
6/21 Banuelos
Imfeld
 
Collected tracker data for monumentation survey (Q1)  