Miscellaneous Ring Alignment
| |
|
Work Week
June 9 To June 15 |
|
|
| Date |
Crew |
Summary |
Photo |
| 6/9 |
McDougal Perry Surbaugh |
Checked screed rails in Q1 |
|
| 6/10 |
Perry Surbaugh |
Surveyed positions of roof blocks
for future BTS raft installation |
|
| 6/10 |
Banuelos Gaudreault |
Checked elevation of new poured
concrete in Q3 |
|
| 6/11 |
McDougal Perry |
Measured height of BTS block 8
inside ring wall |
|
|