Metrology Department
 

Miscellaneous Alignment



 
Work Week
June 2 To June 8
 



Date Crew Summary Photo
6/2 Griffin
Juarez
 
Started Fiducializing BL11 Moveable Mask  
6/2 Carrillo
Gaudreault
 
QC templates with tracker
6/3 Griffin
Juarez
 
Continued with BL11 Moveable Mask  
6/3 Carrillo
Gaudreault
 
QC templates with tracker  
6/4 Gaudreault
Griffin
 
Finished BL11 Moveable Mask and started BL10 Moveable Mask  
6/4 Carrillo
Gaudreault
 
Bld 750 final alignment on raft 78  
6/5 Gaudreault
Griffin
 
Finished BL10 Moveable Mask and started BL6 Moveable Mask  
6/6 Griffin
Juarez
Rogers
 
Continued with BL6 Moveable Mask
6/6 Banuelos
Gaudreault
Perry
 
Fiducialized BL 7 Wiggler Chamber in clean room.