Metrology Department
 

Bend Magnet Beamline Alignment



 
Work Week
May 12 To May 18
 



Date Crew Summary Photo
5/12 McDougal
Perry
 
BL3: Set 2 mirror tanks
5/13 McDougal
Perry
 
BL3: Set BL3-3 and streering line. Found BL3-1 out
5/14 McDougal
Perry
 
BL3: All components set.
Realign bend magnet beamline (IN1175) out of alcove phase with exception of BL1-4 (coffin room) completed.

- Top -
Last update: April 11, 2007