Miscellaneous Ring Alignment
| Date |
Crew |
Summary |
Photo |
| 5/6 |
Perry |
QC contractor cut points in SPEAR ring |
|
| 5/7 |
Banuelos Imfeld |
QC contractor cut points in SPEAR ring |
|
| 5/8 |
Banuelos Imfeld |
Checked 2 cut points and 6 elevations in the SPEAR ring |
|
| 5/9 |
Banuelos Gaudreault |
Checked 5 elevations in north section of SPEAR ring |
|
|