Metrology Department
 

Miscellaneous Alignment



 
Work Week
April 28 To May 4
 



Date Crew Summary Photo
4/28 Gaudreault
Griffin
 
Bld 750: Pre-align raft 83  
4/29 Gaudreault
Griffin
 
Bld 750: Re-aligned corrector stands raft 75, 76
Set-up wire at magnet measurements for septum
 
4/30 Gaudreault
Griffin
 
Bld 750: Set chambers in raft 75 & 76  
5/1 Gaudreault
Griffin
 
Bld 750: Final Align Raft 76 and part of 75  
5/2 Gaudreault
Griffin
Imfeld
Rogers
 
IR12: Set 2 quads (Q8 and Q9) on the new BTS (yellow) raft
5/2 Gaudreault
Griffin
 
Bld 750: Finished final alignment of Raft76
Test fit chamber on Raft 83
BTS raft (in the PM)
 