| Date |
Crew |
Summary |
Photo |
| 4/21 |
Banuelos Perry |
Punched all the extreme (first and last) plugs of all 4 BLs |
|
| 4/22 |
McDougal Perry |
Scribed all the intermediate plugs Installed 2 more plugs
in BL8 |
|
| 4/23 |
McDougal Perry |
Scribed the 2 new plugs in BL8 Stamped date and values on
plugs |
|
| 4/24 |
Imfeld Perry |
Mapped brass plugs. Measured existing plugs for beam lines:
4, 5, 6, 11, and 12. |
|
| 4/24 |
Gaudreault Imfeld McDougal Perry |
Checked values for all recently installed plugs
Set bend magnet beamline monuments (IN1170) completed |
|