Miscellaneous Alignment
| Work Week April 14 To April 20 |
| Date | Crew | Summary | Photo |
|---|---|---|---|
| 4/15 | Gaudreault Griffin |
Started fiduacialization of BL6-2 M0 4 jaw slits tank | |
| 4/16 | Gaudreault Griffin |
Continued with fiducialization of BL6 slit tank | |
| 4/17 | Gaudreault Griffin |
Continued with fiducialization of BL6 slit tank Worked on top vertical slit |
|
| 4/18 | Gaudreault Griffin |
BL 6-2 4 Jaw Slit |