Stanford Linear Accelerator Center Alignment Engineering Down 2004 TimeLine

August 2004

September 2004  PEP-II Alignment Schedule

October 2004

Sunday

Monday

Tuesday

Wednesday

Thursday

Friday

Saturday

 

 
   
 
 
 

 

 
   
 
 
 

 

 
   
 
 
 

1

 Quad Roll

 Sext Offset


 

2

 Quad Roll

 Sext Offset


 

3

 Quad Roll

 Sext Offset


 

4

 

 
   
 
 
 

5

 

 
   
 
 
 

6

  LABOR DAY


 
 
 
 

7

 Quad Roll


 
 
 
 

8

 Quad Roll


 
 
 
 

9

 

 
   
 
 
 

10

 

 
   
 
 
 

11

 

 
   
 
 
 

12

 

 
   
 
 
 

13

 LER RF Cavity

  Align station 4-2
  cavity
 
 
 

14

 

 
   
 
 
 

15

 

 
   
 
 
 

16

 TFB Raft

  Prelim alignment
 
 
 
 

17

 

 
   
 
 
 

18

 

 
   
 
 
 

19

 

 
   
 
 
 

20

 TFBs
  Final alignment


 SLM
 Pumping chamber
 

21

 

 
   
 
 
 

22

 

 
   
 
 
 

23

 

 
   
 
 
 

24

 SLM

  Check graphite
  filter assy
 
 
 

25

 

 
   
 
 
 

26

 

 
   
 
 
 

27

 SLM

  Check BPM &
  X-ray pinhole
  assembly
 
 

28

 SLM

  Check detector
  assembly
 
 
 

29

 

 
   
 
 
 

30

 SLM

  Final alignment
  of exit beamline
 
 
 

 

 
   
 
 
 

 

 
   
 
 
 

Alignment Engineering Group