 Project Number  Description

 Project Manager

 Area Manager
 PBU-121  Check position of comps near Babar  Metcalfe  (x8694)  Zurawel  (x4116)
 PBU-122*  Re-check comps near Babar  Metcalfe  (x8694)  Zurawel  (x4116)
 PBU-208*  Checks up to zone 4 pps gate  Metcalfe  (x8694)  Zurawel  (x4116)
 PBU-706  Pre-align new pumping chamber  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-707  Layout hole pattern for new supports  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-316  Preliminary alignment of raft assembly  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-364  Preliminary alignment of raft assembly  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-367  Final kickers / raft alignment  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-319  Final kickers & raft alignment  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-725  Final alignment of exit beamline  Kharakh  (x3215)  Zurawel  (x4116)
 PBM-700  Quad roll survey  Wienands  (x3817)  Zurawel  (x4116)
 PBM-701  Sextupole offset survey  Wienands  (x3817)  Zurawel  (x4116)
 PBU-709A*  Align check SLM - exit beamline comps  Kharakh  (x3215)  Zurawel  (x4116)
 PBU-720A  Align check - graphite filter assy  Kharakh  (x3215)  Zurawel  (x4116)
 PBM-721A  Align check - BPM & X-ray pinhole assy  Kharakh  (x3215)  Zurawel  (x4116)
 PBM-722A  Align check - Detector Assy  Kharakh  (x3215)  Zurawel  (x4116)
 PBM-702 (PIM-190)  Verify align of PI-11 devices  Iverson  (x2361)  Zurawel  (x4116)
 PIM-190 (PBM-702)  Check align high energy inject IR-10  Iverson  (x2361)  Smith  (x2413)
 PBU-407  Align cavities LER RF Stn 4-2  Hill  (x4453)  Zurawel  (x4116)
 PBU-725  Final alignment of exit beamline  Kharakh  (x3215)  Zurawel  (x4116)
 L-HPR-030 (Linac)  Align quad 991 after rebuild (Sector 2)  Fant  (x4466)  Graul  (x3655)
 L-HPR-390 (Linac)  Remove roll from asset struct (Sector 2)  Ratcliffe  (x3632)  Graul  (x3655)
 L-HPR-440 (Linac)  Align asset structure (Sector 2)  Ratcliffe  (x3632)  Graul  (x3655)
 D-MMR-080 (SLTR)  Align SLTR QF1085 (South Linac to Ring)  Wright   Burrows  (x3888)





04/08/2004

Downtime Summary

04/27/2004

Tiltmeter Study

05/28/2004

Leveling Investigation