View the entire chapter in a PDF format. Please use the pdf for printing.
Requirements:
Procedures and Specific Requirements (5.2)
All SLAC-owned CGCs must be inspected, stored, used, handled, and
transported according to the following specific requirements. For a list of
all implementing documents, see Exhibits, Forms &
Tools.
Note: Subcontractor-owned CGCs are subject to the same requirements except for the purchase of gas and the point of delivery inspection.
Purchasing
Steps to follow to purchase compressed gas (Hazardous Materials: Purchasing Procedure
[pdf])
Inspection
Required monthly inspection (Hazardous Materials: Storage Inspection Procedure and Form
[doc] [pdf] )
Required point of delivery inspection (CGC: Point of Delivery Inspection Form
[doc]
[pdf])
CGC-specific inspection requirements and additional information (CGC: Inspection Requirements
[pdf], and
CGC: Leak Detection Requirements [pdf])
Handling and Use
Handling and use requirements (CGC: Safety Requirements
[pdf],
CGC: Handling and Use Requirements
[pdf], and
CGC: Portable Oxygen-fuel for Welding and Cutting Requirements
[pdf])
Storage
Storage and segregation requirements (CGC: Storage Area Requirements [pdf])
Transport
Restrictions and requirements for on-site transport (CGC: Transport Requirements
[pdf])
continue to Training (5.3)
|