Sample Asbestos Exposure Assessment


Process: Removal of Asbestos Containing Floor Tiles and Mastic
Locations: Site Wide
Hazard: Asbestos fibers


Hazard Control

Work Practices
  • Contact Asbestos Supervisor x4105 via phone or email.
  • Do not eat, drink, or smoke at work site.
  • No power tools may be used to remove floor tiles
  • Use a spray bottle with soapy water to wet floor before and after removing floor tiles.
  • Maximum 2 hours of floor tile removal per day or 1 waste bag.
Training:
  • Mandatory Requirement - ESH Course 151 Class 2 Asbestos Worker within the last 12 months
Housekeeping:
  • Do not use a broom to dry sweep.
  • Clean up WET dust with a wet paper towel.
Waste Management:
  • Turn waste in to the non friable asbestos waste container. Contact Hazardous Waste Management. at x2399